No.

Marking Type

Pavement Marking

Pavement Configuration

1

Lane Open

6" White + 6" Green + 6" Spacing

2

Lane Closed

6" White + 6" Green + 6" Spacing

3

Right Turn Single Lane Ramp Closure

6" White + 6" Green + 6" Spacing

4

Right Turn for Single Lane right ramp closure

6" White + 6" Green + 6" Red + 6" Spacing

5

Merge Right

6" White + 6" Green + 6" Spacing

6

Left Turn Two-Lane Ramp-Left Lane Closure

6" White + 6" Green + 6" Red + 6" Spacing

7

Left Turn Two-Lane Ramp-Right Lane Closure

6" White + 6" Green + 6" Red + 6" Spacing

8

Left Turn Single Lane Ramp Closure

6" White + 6" Green + 6" Red + 6" Spacing

9

U-Turn

6" White + 6" Green + 6" Red + 6" Spacing

10

Start Work Zone

2 × 3" White + 6" Yellow + 6" Green

11

End Work Zone

2 × 3" White + 6" Yellow + 6" Red

12

Work Zone Edge Line (Contrast Pavement Marking)

2 × 3" White + 6" Yellow