| Cause of Time Overrun | Mean Rank | Rank |
| Income and money related troubles looked by temporary workers | 13.8 | 1 |
| Contractual worker’s poor site the board | 12.74 | 2 |
| Insufficient contractual worker experience | 12.61 | 3 |
| Lack of site laborers | 12.36 | 4 |
| Insufficient arranging and booking by temporary workers | 12.18 | 5 |
| Acceleration of material costs | 11.27 | 6 |
| Practice of appointing agreement to most reduced bidder | 11.01 | 7 |
| subcontractors Issues | 10.47 | 8 |
| Absence of correspondence among parties | 10.32 | 9 |
| Change the board | 9.69 | 10 |
| Late in material acquirement | 9.66 | 11 |
| Awkward fashioners | 9.46 | 12 |
| Poor gauge venture span | 8.07 | 13 |
| Low speed of basic leadership | 6.11 | 14 |
| Unanticipated ground condition | 6 | 15 |
| Changes in extent of ventures during development work | 5.93 | 16 |
| Successive structure changes | 5 | 17 |
| Proprietor impedance in development work/process | 4.31 | 18 |