Item

Description

Qty

Unit

Rate (GH¢)

Total (GH¢)

1

Earthworks

Filling in layers not exceeding 225 mm thick in making up levels under floors

540

32.00

17,280.00

2

Concrete Work

Plain in-situ concrete (1:3:6 - 40 mm aggregate) as described in foundation trenches

60

350.00

21,000.00

Ditto in 150 mm floor bedspread and levelled

810

m2

52.00

42,120.00

Reinforced in-situ vibrated concrete (1:2:4 - 20 mm aggregate) as described filled into formwork and around reinforcement (both measured separately)

Horizontal beam/Columns

11

370.00

4070.00

Column

5

370.00

1850.00

3

Supply and fix as described the following mild steel round bar reinforcement with and including all necessary binding wires:

-

12 Diameter bars in column base

2500

Kg

3.40

8500.00

16 mm Diameter bars in column

4440

Kg

3.40

15,096.00

4

Sawn formwork as described to:

The vertical side of the column

316

m2

15.00

4740.00

5

Blockwork

150 mm Solid sandcrete block work in cement mortar (1:4) as described

1499

m2

40.00

59,960.00

6

Plastered/Rendered/Roughcast Coatings

20 mm Cement and sand render to the wall

210

m2

8.00

1680.00

10 mm thick floor tiling, Ceramic Wall Tiling

810

m

45.00

36,450.00

7

Painting/Clear Finishing

Prepare and apply three coats of emulsion paint on rendered wall

210

m2

7.60

1596.00

Prepare and apply three coats of approved Coral emulsion paint on: -

Internal and External walls

1405

m2

4.20

5901.00

Plastic T & G Ceiling including all necessary accessories as described

Ceiling lining nailed to the soffit of hardwood

810

m2

30.00

24,300.00

8

Joinery

Wrought hardwood as described

44 mm (Finished) Panelled door size 900 × 2100 mm high

42

No

230.00

9660.00

50 mm × 150 mm Frame plugged

600

m

18.00

10,800.00

9

Carpentry

Structural timbers, Sawn treated hardwood

Hoist timber truss, Howe pattern, 50 × 150 mm comprising 2Nr Rafters, 1Nr king post and 2Nr bottom chord, 50 × 100 members comprising 4Nr ties, 4Nr structs, 13 m clear span eaves projections.

13

No

500.00

6500.00

50 × 150 mm bottom chord

510

m

12.00

6120.00

50 × 50 mm Nogging

1635

m

4.20

6867.00

50 × 50 mm Joist

1635

m

4.20

6867.00

10

Metalwork

“Naco” anodised aluminium louvre carriers

Pair 1143 mm long with clips for 8 No.

150 mm blades

80

No

60.00

4800.00

16 mm diameter mild steel burglar-proof bar

560

m

5.00

2800.00

11

Roofing

Corrugated aluminium sheet roofing

0.5 mm Gauge Long Span Corrugated Aluminium deep troughed trapezoidal roof sheeting as manufactured by Messrs Ghana Aluminium Products, Tema or equal and approved (fixed to manufacturer’s specifications)

Roof Sheeting

1053

m2

38.00

40,014.00

12

Glazing

6 mm thick “NACO” louvre blades, fixing to metal

800 mm long × 150 mm wide

640

No

3.30

2112.00

Total cost base on the 25% Rule analysis

341,083.00

Original Adjusted Total Cost base on the BOQ

457,721.50

Determine the Percentage

341083.00 457721.50

0.7452

Therefore, Actual Percentage = 0.7452 × 100

74.52%