Task | No-wind duration (day) | Predecessor | |
1 | Erection of Tower of Wind Turbine | ||
1-1 | Lifting & Installing Tower (Lower, Middle, & Upper) | 1 | |
1-2 | Lifting & Installing Nacelle and Generator | 1 | 1-1 |
1-3 | Lifting & Installing Rotor Hub and Blades | 1 | 1-2 |
2 | Cable Laying & Wiring in Tower & Nacelle | 3 | 1-3 |
3 | Commissioning Test & Inspection | 3 | 2 |
4 | Function Co-Test with Owner | 1 | 3 |
5 | Test Run & 96-hr Trial Operation | 4 | 4 |