| Bus No. | Generation (MW) | Load (MW) | LMP ($/MWh) |
| 1 | 195.44 | - | 36.819 |
| 2 | 36.37 | 21.70 | 38.382 |
| 3 | 0 | 24.20 | 39.818 |
| 4 | - | 67.80 | 40.574 |
| 5 | - | 17.60 | 40.085 |
| 6 | 10.33 | 11.20 | 40.206 |
| 7 | - | - | 40.546 |
| 8 | 26.83 | - | 40.537 |
| 9 | - | 29.50 | 40.550 |
| 10 | - | 19.00 | 41.048 |
| 11 | - | 13.50 | 41.106 |
| 12 | - | 16.10 | 41.619 |
| 13 | - | 13.50 | 41.330 |
| 14 | - | 24.90 | 42.392 |
| Operating cost | 8119.82 ($/hr) | Carbon tax | 17.7750$/hr |
| LOLE | - | LOEE | - |