Main Delay Factor | Sub Factor | Responsible Department | Action |
Resource arranging time | Searching time for a skilled operator | Production | Need skill matrix, need at least multi-skilled operator |
Reluctances of worker | Tagging | ||
No prior planning about the placement of workers | Industrial Engineering | Comparing the drawing layout previous & new style | |
No prior planning about the place element of the machine | Analysis of Sample and pilot run stage | ||
Waiting for input | Production | Proxy machine | |
No critical operation analysis | Industrial Engineering | Analysis of Sample and pilot run stage | |
No drawing of the layout | Drawing layout previous & new style | ||
Machine setting time | No attachment in an extra machine | Maintenance | Attachment in the extra machine beforehand |
Going dept. to take tools | Need machine toolbox | ||
Technician time with a mechanic | Pattern/Guide problem | Technical | Need feeding box |