Main Delay Factor

Sub Factor

Responsible Department

Action

Resource arranging time

Searching time for a skilled operator

Production

Need skill matrix, need at least multi-skilled operator

Reluctances of worker

Tagging

No prior planning about the placement of workers

Industrial Engineering

Comparing the drawing layout previous & new style

No prior planning about the place element of the machine

Analysis of Sample and pilot run stage

Waiting for input

Production

Proxy machine

No critical operation analysis

Industrial Engineering

Analysis of Sample and pilot run stage

No drawing of the layout

Drawing layout previous & new style

Machine setting time

No attachment in an extra machine

Maintenance

Attachment in the extra machine beforehand

Going dept. to take tools

Need machine toolbox

Technician time with a mechanic

Pattern/Guide problem

Technical

Need feeding box