CATEGORIES

PROBLEMS

EFFECT

SOLUTIONS

PEOPLE

Grossly under staff

Ineffectiveness

Redeployment/Employment of required skilled personnel

Work Overload

Reduced Productivity/Fatigue

Redeployment of required skilled personnel

PROCESS

Poor standards or procedures

Inconsistencies within the system

Improvements to manual (SOP)

Less environmental focus

causing a lot of damage to the environment

Environmental focus

EQUIPMENT

Inadequate Machines for environmental works

under production

Provision of required plant and equipment

Lack of maintenance

frequent breakdown

Improved maintenance culture

MATERIAL

Poor quality raw materials used

Unreliable results From Field Operation

Tolerable level set for quality control of material usage

Inaccurate ordering/procurement procedures

Substandard material used

Enforcement of Procurement instructions/manuals