3

Other Costs

Shuttering materials

60 pcs of timber

NA

1.25

75.00

Transport

37.50

Outlet covers (student and staff kitchens)

2

NA

4.38

8.76

Training of biogas users

2

days

NA

125.00

Subtotal

246.26

4

Labour

Mason (skilled)

2

NA

5.00 per day for 30 days

300.00

Casual labour (water/construction)

6

NA

37.5

225.00

Plumber

2

NA

5.00 per day for 10 days

100.00

Subtotal

625.00

5

Administration

Board & Lodgings

1

NA

25.00 per day for 30 days

750.00

Communication

1

NA

1.45 per day for 30 days

43.50

Consultation, reporting, supervision fee

1

NA

21.00 per day for 30 days

630.00

Transport/fuel

1

NA

12.50 per day for 30 days

375.00

Survey

1

NA

31.25 per day for 2 days

62.50

Subtotal

1861.00

Grand Total

5277.57