Activities

Execution period

Execution period

2019/2020 dry campaign

2019/2020 dry campaign

Main channel cleaning

18-23/12/2019

13-16/06/2020

Secondary channel cleaning

24-30/12/2019

17-20/06/2020

Pre-germination

02-05/01/2020

21-23/06/2020

Establishment of nurseries

06-10/01/2020

24-26/06/2020

Mud

01/07/2020—02/12/2020

06/25/2020—07/31/2020

Transplanting

01/15/2020—05/02/2020

09-21/07/2020

Water stops

05/10/2020

10/15/2020

Harvest

15-31/05/2020

20/10/2020