Description

No. of

Item

Schedule

(Plan/Actual)

General

1 week after

Coordination Procedure

1

Document Control Procedure

1

Document Numbering System

1

Document Control Index

1

Equipment Numbering System

1

Bi-Weekly Report

1

2 weeks after

Project Management

1 week after

Project Description

1

Project Schedule

1

Project Execution Plan

1

Applicable Codes and Standards

1

Study, Review, and Report

Site Survey Result Report

1

Calculation and Simulation Result Report

5

Additional Document in Total

8

Process

1 week after

Process Basis of Design

1

Process Description

1

Process/Utility Flow Diagram

2

Additional Document in Total

5

Mechanical

1 week after

Tank Type Selection Report with GA Eng’g. Drawing

2

Maintenance and Sparing Philosophies

1

LNG shipping and Tank Capacity Study Report

1

Additional Document in Total

7

Piping

1 week after

Piping Design Philosophy

1

Piping Routing Plan

1

Additional Document in Total

2

Electrical

1 week after

Electrical Design Philosophy

1

Cables Routing Plan

1

Additional Document in Total

3

Instrumentation and Controls

1 week after

Instrument & Control Philosophy

1

Fire & Gas Detection Philosophy

1

Overall Instrument & Control System Diagram

1

Additional Document in Total

3

Civil and Structural

1 week after

Civil and Structural Design Philosophy

1

Plant Layout Philosophy

1

Overall Plot Plan

1

Additional Document in Total

5

Marine

10

1 week after

Architectural

3

1 week after

Fire Fighting

3

1 week after

Safety

4

1 week after

Cost Estimation

1

last week

Schedule (EPC)

1

last week