Description | No. of Item | Schedule (Plan/Actual) |
General |
| 1 week after |
Coordination Procedure | 1 |
|
Document Control Procedure | 1 |
|
Document Numbering System | 1 |
|
Document Control Index | 1 |
|
Equipment Numbering System | 1 |
|
Bi-Weekly Report | 1 | 2 weeks after |
Project Management |
| 1 week after |
Project Description | 1 |
|
Project Schedule | 1 |
|
Project Execution Plan | 1 |
|
Applicable Codes and Standards | 1 |
|
Study, Review, and Report |
|
|
Site Survey Result Report | 1 |
|
Calculation and Simulation Result Report | 5 |
|
Additional Document in Total | 8 |
|
Process |
| 1 week after |
Process Basis of Design | 1 |
|
Process Description | 1 |
|
Process/Utility Flow Diagram | 2 |
|
Additional Document in Total | 5 |
|
Mechanical |
| 1 week after |
Tank Type Selection Report with GA Eng’g. Drawing | 2 |
|
Maintenance and Sparing Philosophies | 1 |
|
LNG shipping and Tank Capacity Study Report | 1 |
|
Additional Document in Total | 7 |
|
Piping |
| 1 week after |
Piping Design Philosophy | 1 |
|
Piping Routing Plan | 1 |
|
Additional Document in Total | 2 |
|
Electrical |
| 1 week after |
Electrical Design Philosophy | 1 |
|
Cables Routing Plan | 1 |
|
Additional Document in Total | 3 |
|
Instrumentation and Controls |
| 1 week after |
Instrument & Control Philosophy | 1 |
|
Fire & Gas Detection Philosophy | 1 |
|
Overall Instrument & Control System Diagram | 1 |
|
Additional Document in Total | 3 |
|
Civil and Structural |
| 1 week after |
Civil and Structural Design Philosophy | 1 |
|
Plant Layout Philosophy | 1 |
|
Overall Plot Plan | 1 |
|
Additional Document in Total | 5 |
|
Marine | 10 | 1 week after |
Architectural | 3 | 1 week after |
Fire Fighting | 3 | 1 week after |
Safety | 4 | 1 week after |
Cost Estimation | 1 | last week |
Schedule (EPC) | 1 | last week |