S/N | Items There is a plan for: | Responses | |||||||||
Strongly agree (5) | Agree (4) | Undecided (3) | Disagree (2) | Strongly disagree (1) | |||||||
F | % | F | % | F | % | F | % | F | % | ||
1. | Setting & achieving of vision, mission, goal & values | 18 | 9.2 | 19 | 9.7 | 7 | 3.6 | 98 | 50.3 | 53 | 27.2 |
2. | Curriculum need assessment | 12 | 6.2 | 19 | 9.7 | 5 | 2.6 | 59 | 30.3 | 100 | 51.3 |
3. | Staffing | 66 | 33.8 | 82 | 42.1 | 29 | 14.9 | -a | -a | 18 | 9.2 |
4. | Staff capacity building | 54 | 27.7 | 100 | 51.3 | 1 | 0.5 | 19 | 9.7 | 21 | 10.8 |
5. | Designing incentive packages | 21 | 10.8 | 17 | 8.7 | 1 | 0.5 | 79 | 40.5 | 74 | 30.88 |
6. | Resource mobilization | 11 | 5.6 | 21 | 10.8 | 1 | 0.5 | 109 | 55.9 | 53 | 27.2 |
7. | Efficient utilization of resources | 58 | 29.7 | 90 | 46.2 | 9 | 4.6 | 22 | 11.3 | 16 | 8.2 |
8. | Budget | 66 | 33.8 | 78 | 40 | 3 | 1.5 | 20 | 10.3 | 28 | 14.4 |
9. | Involving stakeholders | 9 | 4.6 | 26 | 13.3 | 3 | 1.5 | 119 | 61.0 | 38 | 19.5 |
10. | Enrollment of adult learners | 64 | 32.8 | 98 | 50.3 | 4 | 2.1 | 20 | 10.3 | 9 | 4.6 |
11. | Post literacy | 9 | 4.6 | 42 | 21.5 | 2 | 1.0 | 55 | 28.2 | 87 | 44.6 |
12. | Averting functional illiteracy relapsing | 7 | 3.6 | 9 | 4.6 | 2 | 1.0 | 102 | 52.3 | 75 | 38.5 |
13. | Monitoring and Evaluation | 2 | 1.0 | 13 | 6.7 | 2 | 1.0 | 135 | 69.2 | 43 | 22.1 |