Main indicators | |
Construction works (started) | 2009 |
Commissioning year (estimated) | 2013 |
Normal operating capacity | 87 hm3 |
Number of units | 3 |
Power | 77 MW |
Annual average capacity | 134 GWh |
Reduction in CO2, equivalent per year | 70 kt |
Estimated investment (ref. 2009) | 171 M€ |
National contribution | 75% to 80% |