Year

Project name

Project contents

Execution unit

2002

Meizuolyu upstream emergency project

Dolosse breakwater 102 pieces

Chenggung Township Administration

2002

Meizuolyu upstream regulation project (1)

Stream regulation 200 m

Soil and Water Conservation Bureau

2003

Meizuolyu Stream regulation project (2)

Stream regulation 300 m and revegetation

Soil and Water Conservation Bureau

2004

Meizuolyu Stream regulation project (3)

Comb-type dam 2 Stone masonry revetment 60 m Ford 1

Soil and Water Conservation Bureau

2005

Meizuolyu Stream regulation project (4)

Submerged dam 2 and revetment 500 m

Soil and Water Conservation Bureau

2008

Meizuolyu Stream regulation project (5)

Ground sill 13 and stream regulation 211 m

Soil and Water Conservation Bureau