Project | Inputs | Outputs | ||||||
Expected Project Cost | Expected Project Duration in Days | Number of Black and Green Belts | Percentage Increase in Customer Satisfaction | Impact on Business Strategy | Financial Impact | Expected Increase in Sigma Quality | Expected Percentage Increase in Productivity | |
1 | 212 | 70 | 10 | 11 | 4 | 331 | 0.24 | 20 |
2 | 199 | 63 | 3 | 29 | 8 | 342 | 0.77 | 23 |
3 | 214 | 88 | 5 | 28 | 4 | 333 | 0.33 | 10 |
4 | 280 | 77 | 8 | 29 | 6 | 303 | 0.48 | 10 |
5 | 263 | 72 | 11 | 19 | 2 | 240 | 0.41 | 11 |
6 | 203 | 70 | 11 | 21 | 5 | 306 | 0.52 | 17 |
7 | 196 | 61 | 3 | 31 | 9 | 345 | 0.78 | 21 |
8 | 215 | 79 | 5 | 22 | 5 | 264 | 0.27 | 6 |
9 | 281 | 71 | 8 | 17 | 3 | 239 | 0.66 | 19 |
10 | 233 | 66 | 6 | 10 | 6 | 338 | 0.3 | 16 |
11 | 263 | 84 | 10 | 27 | 8 | 310 | 0.88 | 19 |
12 | 198 | 60 | 3 | 32 | 8 | 341 | 0.51 | 22 |
13 | 220 | 80 | 4 | 15 | 7 | 308 | 0.31 | 7 |
14 | 284 | 79 | 6 | 23 | 4 | 325 | 0.31 | 7 |
15 | 214 | 87 | 7 | 19 | 7 | 314 | 0.54 | 5 |
16 | 235 | 80 | 5 | 27 | 2 | 236 | 0.34 | 17 |
17 | 200 | 63 | 4 | 33 | 8 | 339 | 0.83 | 23 |
18 | 217 | 75 | 11 | 13 | 5 | 313 | 0.74 | 7 |
19 | 198 | 63 | 3 | 31 | 8 | 343 | 0.87 | 22 |
20 | 227 | 70 | 5 | 10 | 6 | 317 | 0.46 | 17 |