Knowledge about the Front-End Planning method | Sector of the organization | Average cost of project | Average duration of project | |||||||||||||||
Oil and Gas | Mining and Metals | Telecommunication | Engineering and Construction | Others | Less than $ 1 Million | Between $ 1 Million and $ 10 Million | Between $ 10 Million and $ 100 Million | Between $ 100 Million and $ 1 Billion | More than $ 1 Billion | Less than 1 year | Between 1 and 2 years | Between 2 and 3 years | Between 3 and 4 years | More than 4 years | ||||
Do not know | 12 | 22% | 2 | 1 | 1 | 6 | 2 | 4 | 1 | 0 | 6 | 1 | 5 | 1 | 3 | 0 | 3 | |
Know but do not apply | 12 | 22% | 4 | 0 | 1 | 6 | 1 | 3 | 3 | 1 | 3 | 2 | 3 | 5 | 1 | 2 | 1 | |
Know and apply | 30 | 56% | 9 | 12 | 0 | 7 | 2 | 1 | 3 | 5 | 12 | 9 | 4 | 3 | 7 | 6 | 10 | |
Total | 54 | 100% | 15 | 13 | 2 | 19 | 5 | 8 | 7 | 6 | 21 | 12 | 12 | 9 | 11 | 8 | 14 |