Turbines | Task type | Time window (day) | Penalty cost (euro/day) | Load requirement (kg) | Personnel requirement | Task duration (hours) |
T3 | Replacement | 3 | 2000 | 800 | 3 | 3 |
T13 | Replacement | 2 | 2500 | 500 | 3 | 2 |
T14 | Repair | 6 | 500 | 50 | 2 | 2 |
T16 | Repair | 5 | 1000 | 300 | 3 | 2 |
T27 | Replacement | 2 | 2500 | 500 | 2 | 3 |
T49 | Replacement | 1 | 3000 | 800 | 4 | 3 |
T54 | Repair | 5 | 1000 | 50 | 1 | 1 |