Assumption | Non-standardized coefficients | S.E. | C.R. | P | Standardized coefficients |
Consequences of risks (Prolong the construction progress) ← Risk from contracts (B1) | 0.211 | 0.087 | 2.416 | 0.016 | 0.136 |
Consequences of risks (Prolong the construction progress) ← Risk from the politics and law (B2) | 0.236 | 0.093 | 2.528 | 0.011 | 0.146 |
Consequences of risks (Prolong the construction progress) ← Risk from techniques (B3) | 0.236 | 0.105 | 2.245 | 0.025 | 0.167 |
Consequences of risks (Prolong the construction progress) ← Risk from natural conditions and social environment (B4) | 0.162 | 0.064 | 2.532 | 0.011 | 0.143 |
Consequences of risks (Prolong the construction progress) ← Risk from economy (B5) | 0.440 | 0.126 | 3.506 | *** | 0.237 |
Consequences of risks (Prolong the construction progress) ← Risk from management (B6) | 0.173 | 0.085 | 2.037 | 0.042 | 0.139 |
Consequences of risks (Prolong the construction pro.) ← Risk from the EPC general contractors (B7) | 0.331 | 0.111 | 2.985 | 0.003 | 0.220 |