Barrier

N

Sum

Mean

Standard Deviation

RII

Ranking

Reliance on Supervisor’s Judgement

Dependence on the opinion of supervisors not grounded on firm data.

60

294

4.90

0.303

98.0

1

Generic and Non-systematic Approach

Method of progress measurement is unspecified in contract documents.

60

288

4.80

0.514

96.0

2

Variable Quality of Data

Different units of measurement employed impacting on duration and accuracy of procession.

60

288

4.80

0.546

96.0

3

Intricate Measurement Reports

Difficulty in generating structured work breakdown to facilitate activity measurement and easy visualization of progress monitoring reports.

60

280

4.67

0.510

93.3

4

Lack of Timely Information

The process is not automated hence cannot facilitate real-time progress measurement and it is also time-consuming.

60

261

4.35

0.732

87.0

5

Laborious Data Gathering

Manual data collection and extraction, as well as tedious calculations, make the process operose, inaccurate and steep.

60

246

4.10

0.543

82.0

6

Quality Integration Constraint

Difficulty in integrating cost, time and scope of work (quality) into the progress measurement.

60

241

4.02

0.892

80.3

7

Frequent Variation in Work

Changing nature of work necessitating corrective measures.

60

231

3.85

0.659

77.0

8

Unrealistic Planning

Inadequate pre-contract planning resulting in increased scope of effort and extensive as-planned data.

60

223

3.72

0.804

74.3

9

Deficient Method Statement

Difficulties in analyzing causes of deviations.

60

212

3.53

0.812

70.7

10

Extension of Time

Measurements related to time are muddled when time changes.

60

196

3.27

0.710

65.3

11

Fixation on Time Data

Using time data only in computing progress.

60

195

3.25

0.751

65.0

12

Fixation on Cost Data

Using cost data only in computing progress.

60

195

3.25

0.751

65.0

13

Contentious Claims

Non-defined work scope and responsibilities, and poor documentation.

60

171

2.85

0.954

57.0

14

Delays and Disruptions

Progress measurement becomes distorted whenever work is interrupted and prolonged reports also delay decision making process.

60

160

2.67

1.052

53.3

15

Unforeseen Site Conditions

The difficulty in taking physical measurement under inclement weather.

60

156

2.60

0.827

52.0

16