Gen. Bus No. | Before the outage | After the outage | Cost deviation ($/hr) | ||
Generation (MW) | Cost ($/hr) | Generation (MW) | Cost ($/hr) | ||
1 | 199.28 | 8915.04 | 130.00 | 9448.23 | 533.20 |
2 | 37.22 | 40.82 | |||
5 | 35.99 | 64.33 | |||
8 | 15.09 | 29.29 | |||
11 | 6.33 | 27.12 | |||
13 | 0 | 1.95 |