Projects

Average of bidders’

Offer (INR)(A)

Project Cost

(INR) (B)

Winner’s offer (INR) (C)

C/A

(%)

C/B

(%)

Pr-1

578,955,819.50

600,000,000.00

541,718,515.00

93.6

90.29

Pr-2

560,045,576.00

652,018,837.12

537,524,143.00

96.0

82.44

Pr-3

148,558,236.00

151,311,616.51

136,120,676.00

91.6

89.96

Pr-4

401,717,221.75

435,735,213.47

372,420,036.00

92.7

85.47

Pr-5

694,344,982.00

729,457,990.25

617,731,977.00

89.0

84.68

Pr-6

552,977,822.33

595,512,890.96

545,262,748.00

98.6

91.56

Pr-7

319,475,425.00

340,769,907.69

309,755,259.00

97.0

90.90

Pr-8

605,285,964.20

623,598,090.96

546,964,937.00

90.4

87.71

Pr-9

537,451,403.80

578,633,246.35

502,877,507.00

93.6

86.91

Pr-10

579,256,642.25

698,333,424.59

453,990,619.00

78.4

65.01

Pr-11

9,864,289.75

10,574,375.56

7,478,718.00

75.8

70.72

Pr-12

18,989,253.50

22,574,375.56

18,817,893.00

99.1

83.36

Pr-13

3,374,055.75

5,566,789.37

2,938,827.00

87.1

52.79

Pr-14

8,276,067.00

9,000,000.00

5,382,798.00

65.0

59.81

Pr-15

88,474,895.67

90,000,000.00

73,470,443.00

83.0

81.63

Pr-16

22,211,877.25

25,000,000.00

18,938,435.00

85.3

75.75

Pr-17

51,589,099.00

52,000,000.00

41,732,546.00

80.9

80.25

Pr-18

65,087,310.20

69,000,000.00

54,024,082.00

83.0

78.30

Pr-19

33,185,996.00

35,000,000.00

32,183,445.00

97.0

91.95

Pr-20

16,047,961.00

19,000,000.00

15,047,356.00

93.8

79.20

Pr-21

11,689,464.95

14,000,000.00

10,588,564.95

90.6

75.63