Type of risk

Work packages

Risk

Probability

Effect on time (month)

Effect on cost (million Rials)

Risk mark

Indirect

-

Financial

0.8

4

77.1

16

Indirect

-

The lack of infrastructure in the region

0.6

2

86.66

12

Indirect

-

Incompetence contractors

0.4

4

27.33

10

Indirect

-

Inability of project owners

0.4

5

38.4

10

Indirect

-

Rules and regulation changes

0.4

2

24.3

10

Direct

Foundation and structure work

Delay in supply

0.4

3

42.2

6.44

Direct

Foundation and structure work

Lack of quality of materials

4.22

2

29.7

6.33

Direct

Foundation and structure work

Military dereliction of duty

0.356

4

26.21

5.73

Direct

Foundation and structure work

Defective equipment

0.378

2

23.2

5.46

Direct

Foundation and structure work

Mistakes in construction

0.312

1.5

36.33

5.19

Direct

Foundation and structure work

Mistakes of construction

0.6

4

24

13

Direct

Foundation and structure work

Events during execution

0.6

1

22

12

Direct

Foundation and structure work

Technical and engineering changes

0.534

3

21

10.67

Direct

Foundation and structure work

Military dereliction of duty

0.534

4

25.7

9.78