Type of risk | Work packages | Risk | Probability | Effect on time (month) | Effect on cost (million Rials) | Risk mark |
Indirect | - | Financial | 0.8 | 4 | 77.1 | 16 |
Indirect | - | The lack of infrastructure in the region | 0.6 | 2 | 86.66 | 12 |
Indirect | - | Incompetence contractors | 0.4 | 4 | 27.33 | 10 |
Indirect | - | Inability of project owners | 0.4 | 5 | 38.4 | 10 |
Indirect | - | Rules and regulation changes | 0.4 | 2 | 24.3 | 10 |
Direct | Foundation and structure work | Delay in supply | 0.4 | 3 | 42.2 | 6.44 |
Direct | Foundation and structure work | Lack of quality of materials | 4.22 | 2 | 29.7 | 6.33 |
Direct | Foundation and structure work | Military dereliction of duty | 0.356 | 4 | 26.21 | 5.73 |
Direct | Foundation and structure work | Defective equipment | 0.378 | 2 | 23.2 | 5.46 |
Direct | Foundation and structure work | Mistakes in construction | 0.312 | 1.5 | 36.33 | 5.19 |
Direct | Foundation and structure work | Mistakes of construction | 0.6 | 4 | 24 | 13 |
Direct | Foundation and structure work | Events during execution | 0.6 | 1 | 22 | 12 |
Direct | Foundation and structure work | Technical and engineering changes | 0.534 | 3 | 21 | 10.67 |
Direct | Foundation and structure work | Military dereliction of duty | 0.534 | 4 | 25.7 | 9.78 |