Zone

Stage office

Development area (DA)

No. of farm units

Irrigated area (du)

Water source

Project name

Northern Jordan Valley (NJV), North Directorate

1

1, 2, 6, 7

365

12,892

KAC, Yarmouk

North Ghor Conversion Project

2

11, 12

365

13,886

KAC, Yarmouk

North Ghor Conversion Project

2

12, 13, 14, 15, 16

584

20,477

KAC, Yarmouk, KTR (ZCIII)

North Ghor Conversion Project

7

3, 4, 5

379

12,525

KAC, Wadi Arab

Wadi Arab Project

7

8, 9, 10, 33, 34, 35, 36, 37, 38, 39

756

28,791

KAC, Dam, Zeglab Dam, Al-Gorom Dam

North East Ghor Project

Sub Total

2449

88,571

Middle Jordan Valley (MJV), Deir Alla Directorate

3

18, 19, 20, 21

498

20,339

KAC, KTR (ZCIII)

North Ghor Conversion Project

4

23

683

25,623

KTR (ZCII), KAC

Middle Ghor Conversion Project

5

24, 25, 30, 54

696

26,582

KTR (ZCII), KAC

Middle Ghor Conversion Project/ZorSheshaa

8

22, 53

383

14,212

KTR (ZCII), KAC

Middle Ghor Conversion Project/Abo Zegan

Sub Total

2260

86,756

Southern Jordan Valley (SJV), Karameh Directorate

8

29

337

11,454

KTR (ZCI)

Zarka Triangle Project

6

26, 27, 28

1,026

39,794

KTR, KAC

18 km extension Project

9

49, 50, 51, 52

1,382

56,600

KTR, KAC, Shueib

14.5 km Project

10

31, 32

458

15,580

Kafrien Dam, Mujeb

Hisban-Kafrain Project

Sub-Total

3203

123,429

Safi, Southern Ghor Directorate

11

40, 41, 42, 43, 44, 45, 46, 47, 48

1552

47,730

Ibn Hammad, & Al-Karak, Mujeb Dam

Southern Ghors Project /stage I

12

55, 56, 57

326

10,217

WadiHisan, Fifa, Tanur dam

Southern Ghors Project /stage II

Sub-Total

1,878

57,947

Wadi Araba

13

58

325

6,500

Ground Water Wells

New Wadi Araba Irrigation Project

Grand Total

10,115

363,203