No. | Companies in charge | Agreement | Service |
1 | Kepinvestment Singapore (Keppel Corporation) | Apr-20 | loan of $87 m to develop the first phase, and hold 40% interest |
2 | Profab (National Oilwell Varco) | 2019 | Facilities wellhead platform |
3 | Offshore Construction Specialist | 2019 | Structural Design the wellhead platform |
4 | Petrovietnam Drilling and Well Service Corporation (PV Drilling) | Aug-20 | Drill five production wells |
5 | Keppel Shipyard (Keppel Offshore & Marine) | Nov-18 | Contract $21 m to modify and upgrade Ingenium II production barge |
6 | Fugro | Jan-20 | Geotechnical survey |
7 | Shearwater Geoservices | Jun-Jul-19 | 3D seismic 1200 km2 |