Indicators | Benchmarking | Company | Site | Median* | Maximum* |
Concreting-pillar | |||||
Waste of concrete (%) | 5.18 | A | A | 6.66 | 17.29 |
Concreting-Beam + slab + pillar complement | |||||
Waste of concrete (%) | 2.00 | A | A | 4.75 | 26.61 |
Sealing masonry | |||||
Waste of blocks/bricks (%) | 0.83 | B | B | 3.50 | 15.00 |
Waste of mortar (%) | 12.34** | C | C | 114.13 | 429.29*** |