Item | Activity | Scale and No. of Response | Total | RII | Ranking | ||||
1 | 2 | 3 | 4 | 5 | |||||
a) | Identifying who would be responsible for resource management | 1 | 15 | 5 | 3 | 4 | 28 | 0.557 | 1st |
b) | Forecasting the types of waste likely to be generated. | 6 | 6 | 9 | 5 | 2 | 28 | 0.536 | 2nd |
c) | Pre-stating how the waste would be managed, e.g. will it be reduced, reused or recycled etc. | 3 | 15 | 3 | 4 | 3 | 28 | 0.521 | 3rd |
d) | Identifying which contractors would be used to ensure that waste is managed safely | 6 | 6 | 12 | 4 | 0 | 28 | 0.500 | 4th |
e) | Estimating the quantity of waste to be generated on the project | 18 | 4 | 3 | 2 | 1 | 28 | 0.343 | 5th |