Task No. | Description | Immediate Predecessors | Duration/[days] |
1 | Preliminary paper sketch | 1 | 1 |
2 | Wing and empennage design investigation & study | 1 | 2 |
3 | Fuselage design investigation & study | 8 | 2 |
4 | BWB UAV assembly and payload investigation & study | 1 | 2 |
5 | Avionics suite investigation & study | 1 | 3 |
6 | Rotor investigation and study | 2 | 1 |
7 | Engine design investigation & study | 4 | 2 |
8 | Conceptual design alternatives | 5 | 3 |
9 | Solid Works Modeling and design | 1 | 4 |
10 | Structural Analysis | 7 | 4 |
11 | Verification and Testing | 10 | 3 |
12 | Solid Works Flow Simulation | 11 | 3 |
13 | Special Component Research and Ordering | 9 | 2 |
14 | Assembly of parts | 3 | 2 |
15 | Flight Testing | 12 | 5 |
16 | Cost Analysis | 17 | 3 |
17 | Report presentation and seminars | 13 | 3 |
18 | Engineering drawings | 11 | 3 |
19 | Distribution of drawings | 16 | 2 |
20 | Making of posters | 14, 15, 18, 19 | 2 |